As UN Confirms ICP Scoop on CMP Overruns, US Mission Only Tweets, Wants Department of Management?
By Matthew Russell Lee
UNITED NATIONS, March 14, updated -- On Monday a cost overrun in the UN Capital Master Plan of $265 million, up from $79 million, was reported by Inner City Press, along with the analysis that this makes it far less likely that another new UN building, the so-called DC-5 or "Ban's Boondoggle," will be built.
On Tuesday the UN confirmed the increased cost overrun and also the additional "associated costs" of $147 million reported by Inner City Press.
But the spokesman for Secretary General Ban Ki-moon, he of the boondoggle, said there was no connection with DC-5, that "is totally unconnected, as you well know, that should anything happen on that front, it is dealt with by an entirely different body — it’s not dealt with by the United Nations itself, and I think you know that."
Inner City Press followed up, with the US and UK Missions to the UN and with Ban's spokesman, Martin Nesirky:
Inner City Press: at least some Member States are saying, although it would be the UN Development Corporation that would actually build DC-5, they are considering now this idea of a contingency plan for the footprint or logistics of the UN. So they see it as connected in this way: if in fact there have been these overruns on repair, what level of confidence do they have? Are you saying that the building of DC-5 could never cost the UN budget money?
Spokesperson: The building, should such a building be constructed, it would be under that Corporation, which is not a UN body, okay?
Many member states' representatives have told Inner City Press they see a connection: once Ban's Secretariat so badly underestimated or understated the costs of the CMP, why gamble more money for a building that may not be necessary (and which, incidentally, would unilaterally destroy a playground)?
A UK spokesman responded to Inner City Press with this: "Fifth Committee is now in session with decisions on the Capital Master Plan needed by the end of next week. We are looking at the detail closely, and are of course concerned at projected cost over-runs."
The US Mission to the UN was twice asked for comment, specifically from its Ambassador for such issues, Joe Torsella. In response, after a day, Inner City Press was directed to Torsella's Tweets on the topic.
These do not address DC-5; notably, many of Torsella's tweets are in fact pro-UN re-tweets, for example about the Lubanga verdict (click here for Inner City Press' story on UN's role with another unindicted child soldier recruiter, Peter Karim), the appointment of a 71-year old Swede to be Ban's deputy, unqualified praise for the "Action Agenda" of Ban Ki-moon, which so far has meant rotating his long time advisers Kim Won-soo and Yoon Yeochol to new but close by jobs, and shifting American Bob Orr to an invented public private partnerships job. Some reform.
On the CMP overruns, Torsella links as "UN101" to a story that undercounted the overrun as 4%.But perhaps, while not stated in Torsella's Twitter profile, retweets are not endorsements. In fairness we note that while not commenting on DC-5, Torsella has tweeted concerns and questions about the CMP overruns:
Notably, the head of the CMP is an American, Michael Adlerstein. Some say the US hopes to take over not only the Department of Political Affairs, but also the Department of Management, perhaps with Patrick Kennedy. The Department of Management oversees the CMP.
So could their be some conflicts of interest, or weakening, in this US Mission's stated commitment to reform the UN? Watch this site.
Tuesday, March 13, 2012
Amid Complaints of $265M UN Repair Overrun, $147M More, No DC5?
By Matthew Russell Lee
UNITED NATIONS, March 12 -- With the UN Security Council full of foreign minister on Monday, some expressed surprise at the stage of the Capital Master Plan reconstruction of the UN, and the cost overruns under Secretary General Ban Ki-moon. Things are worse than they know.
Last week, CMP Assistant Secretary General Michael Adlerstein belatedly told member states that cost overruns now are $265 million, compared to a previous disclose of less of $80 million, supposedly whittled down through something called value engineering.
But even this $265 million overrun understates the problem, as it does not include so-called "associated costs." According to the document A/66/527/Add.1, "the resources required for associated costs for the period from 2008 to 2013 are estimated to total $146,806,000."
So the actual CMP cost overrun under Ban and Adlerstein is $412 million. Recently there was a push to override local opposition and make plans to build another new UN building, tentatively called DC-5, on the playground to the south of 42nd Street, where currently children play sports, and adults soccer in the afternoon.
Now, sources tell Inner City Press, the idea of the UN building yet another building seems "absurd," with the over $400 million overrun on a mere reconstruction. Watch this site.
Footnote: Inner City Press alluded to this coming disclosure last week, even as a major wire service (mis) reported that the CMP cost overrun was "only" four percent.
Meanwhile the UN has refused to answer Inner City Press' repeated questions about who is getting paid by the UN to accompany Kofi Annan to Syria -- TV images show for example former UN official Alan Doss, who left amid a nepotism scandal in which he asked UNDP to bend or break its rules to give a job to his daughter -- and about the propriety of the return as a UN adviser of another former official, Maurice Strong, who left amid the Oil for Food scandal, and another bout of nepotism.
Mismanagement and corruption may be different things -- but lack of transparency in the use of public money fuels both of them. Watch this site.